Week of Sept. 21, 2026 In progress
Sheet metal wraps up as the elevator goes to final inspection
Here's what's planned for September 21–25, and what to expect as the
work moves ahead. With ongoing utility relocation work at The Dalles Pathway this week,
watch for signage and crew directions. Expect sheet metal work at Buildings 2 and 4, and
utility and concrete work near Building 5. Summer construction is nearly complete.
- Roof: sheet metal at Buildings 2 and 4, Monday through Saturday, with the roofing crew demobilizing Sept. 28.
- Elevator: corrections finalized and tested Monday, with final inspection Tuesday, Sept. 22.
- Site and paving: the new walkway to Building 5 concrete ramp prep and pour, Monday through Wednesday, and its hand rail Wednesday through Friday. Erosion control and seeding Monday and Tuesday.
- Utility relocation along The Dalles Pathway, Monday through Friday.
- Building 3 staircase replacement: complete.
- Wayfinding: in permitting with the city, and Tube Art is producing the signage.
Week of Sept. 14, 2026 Complete
Handrail work at The Dalles parking area; Building 2 roofing continues
Here's what's planned for September 14–18, and what to expect as the
work moves ahead. With ongoing handrail work at The Dalles parking area this week, watch for
signage and crew directions. Expect roofing noise at Building 2 and handrail work near The
Dalles parking area. Summer construction is nearly complete.
- Roof, Building 2: roofing installation Monday through Saturday, with sheet metal at Buildings 2 and 4 Monday through Saturday. Hot tar will only occur after hours and on weekends, and the skylight is scheduled for delivery Sept. 17 and 18.
- Elevator: making corrections from last week's inspection.
- Site and paving: handrail fabrication and installation at The Dalles parking area, Monday through Friday, and the new walkway to Building 5 concrete ramp handrail, Monday through Friday.
- Building 3 staircase replacement: complete.
- Wayfinding: in permitting with the city, and Tube Art is producing the signage.
Week of Sept. 7, 2026 Complete
Building 2 roofing, handrail work and paving continue
Roofing, paving, and elevator work continue across campus. Here's what's planned for
September 7–13, and what to expect as the work moves ahead.
Handrail, ramp, and generator pad work runs at The Dalles parking area and the Hood River
Center Tuesday through Friday, with striping following Thursday and Friday. Watch for
signage and crew directions. Expect roofing noise at Buildings 2 and 4, and construction
activity near The Dalles parking area and the Hood River Center this week.
- Roof, Building 2: tear-off Tuesday through Thursday, roofing installation and sheet metal Tuesday through Saturday, and lower HVAC curb work Thursday and Friday.
- Roof, Building 4: roofing installation Friday and Saturday, sheet metal Tuesday, and stucco repair Friday and Saturday.
- Elevator: final inspection Tuesday, Sept. 8.
- Site and paving: handrail fabrication and installation at The Dalles parking area and Alt. No. 3, and Alternate No. 4 concrete ramp prep and pour, Tuesday through Friday, then striping at Parking Lots #1, #2 and #4 and The Dalles parking area, Thursday and Friday.
- Hood River Center: generator pad prep and pour, Tuesday through Friday.
- Building 3 staircase replacement: complete.
- Wayfinding: in permitting with the city, and Tube Art is producing the signage.
- Dates worth noting: hot tar work moves to after hours and weekends, and the skylight is scheduled for delivery Sept. 17 and 18.
Week of Aug. 31, 2026 Complete
The Dalles excavation, Hood River paving prep and Building 2 roofing continue this week
Roofing, paving, and elevator work continue across campus this summer. Here's what's planned
for August 31 – September 4, and what to expect as the work moves ahead.
The Dalles parking area at Building 2 is closed for excavation and rock work
Monday through Wednesday, then again Thursday and Friday for paving and striping along with
Parking Lots #1, #2 and #4. Watch for signage and crew directions. Expect excavation and
paving noise near The Dalles and Hood River sites, and roofing work at Building 2 all week.
- Roof, Building 2: roofing installation Monday through Saturday, with sheet metal Monday through Saturday.
- Elevator: punch list.
- Site and paving: The Dalles parking area excavation and rock, Monday through Wednesday, Aug. 31 to Sept. 2, then paving and striping at Parking Lots #1, #2 and #4 and The Dalles parking area, Thursday and Friday, Sept. 3 and 4.
- Hood River Center: generator pad prep and pour, Monday through Wednesday, Aug. 31 to Sept. 2.
- Building 3 staircase replacement: complete.
- Wayfinding: in permitting with the city, and Tube Art is producing the signage.
Week of Aug. 24, 2026 Complete
Elevator final inspection; excavation and rock at The Dalles parking area
Roofing continued at Buildings 2 and 4 while site crews worked at The Dalles parking area
and across the Hood River Center. The elevator reached final inspection.
- Roof, Building 2: roofing installation and sheet metal, Monday through Saturday, with hot tar Monday through Wednesday.
- Roof, Building 4: sheet metal, Monday through Wednesday.
- Building 2 HVAC: Tuesday and Wednesday.
- Elevator: final inspection.
- Site and paving: excavation and rock at The Dalles parking area, Monday through Friday, Aug. 24 to 28.
- Hood River Center: pressure washing Monday and Tuesday, crack seal, sealcoat, and striping Monday through Wednesday, and generator pad prep and pour Monday through Friday.
Week of Aug. 17, 2026 Complete
Grinding and paving prep at Parking Lots #1, #2 and #4
Roofing, paving, and elevator work continue across campus this summer. Here's what's
planned for August 17–21, and what to expect as the work moves ahead.
Parking Lots #1, #2 and #4 see grinding Monday and Tuesday and paving prep
Tuesday through Friday, so expect detours and limited parking all week — watch for
signage and crew directions. Expect grinding and paving noise plus asphalt odor near the
parking lots all week, and hot tar work at the Building 2 and Building 4 roofs Monday
through Friday.
- Roof, Building 2: tear-off Monday through Wednesday, and roofing installation Monday through Saturday.
- Roof, Building 4: roofing installation Monday through Friday, completing Friday, with sheet metal Monday through Friday.
- Elevator modernization: punch list this week, with the crew demobilizing the week of Aug. 24.
- Site and paving: grinding at Parking Lots #1, #2 and #4 Monday and Tuesday, paving prep at those lots Tuesday through Friday, and excavation and rock at The Dalles parking area beginning Friday.
- Hood River Center: crack seal, sealcoat, and stripe Thursday and Friday.
- Coming the week of Aug. 24: Building 2 sheet metal, Building 2 HVAC, Hood River pressure wash, and the Hood River generator pad.
Week of Aug. 10, 2026 Complete
Repaving at The Dalles parking area; east stair wraps up
Paving crews are scheduled at The Dalles parking area and Parking Lot #3 Monday through
Friday. Expect continued detours and limited parking in that area through the week. The
east stair replacement finishes and that crew demobilizes Thursday.
- East stair: tread and landing grating installed Monday and Tuesday, riser faces Tuesday, cleanup Wednesday, and the crew demobilizes Thursday.
- Elevator: final inspection is scheduled this week, with the punch list to follow the week of Aug. 17 and the crew demobilizing the week of Aug. 24. Dates are tentative.
- Roof, Building 2: roofing installation continues Monday through Saturday, with tear-off work carrying into the following week.
- Roof, Building 4: roofing installation finishes Friday, with sheet metal installed Monday through Friday.
- ADA pathways and parking: asphalt paving and striping at The Dalles parking area and Parking Lot #3, Monday through Friday, and concrete installation at the parking area on Monday.
- Hood River Center: pressure washing begins Friday, continuing the following Monday.
Week of Aug. 2, 2026 Complete
Parking Lot #3 closes as paving and painting begin
Parking Lot #3 closed Tuesday, Aug. 4 while crews grind the lot ahead of
repaving on Monday, Aug. 10. The main drive aisle to Parking Lot #2 stays open.
- East stair: second-phase sandblasting Tuesday, then painting of all components Wednesday through Friday. Expect noise Tuesday.
- West stair: joint sealants at the brick veneer column Wednesday.
- Elevator: demolition of the existing equipment.
- Roof, Building 2: torch-down built-up roofing on the lower roof sections at the Bookstore, with tear-off continuing on the upper roofs.
- ADA pathways and parking: concrete continuing at The Dalles parking area, the stairs, and the Building 5 ADA work, plus grinding and paving at the parking area and Parking Lot #3.
- An existing utility conflict along The Dalles Pathway and the ADA path from Building 3 to the connecting path is still being resolved and may affect the schedule.
Week of July 27, 2026 Complete
Stair steel, elevator fixtures, and campus concrete
Four projects are active in the field at The Dalles Campus this week.
- East stair: joint sealants at the brick veneer column, new tread support angles, and new steel tied into the existing structure, with second-phase sandblasting Friday.
- Elevator: hall fixtures, hall door equipment, car door equipment, and car fixtures being installed.
- Roof: Building 4 being completed and tear-off underway at Building 2.
- ADA pathways and parking: concrete at Buildings 2 and 4, a valley gutter and curb pour, and concrete work in The Dalles parking area.
Week of July 19, 2026 Complete
Stair demolition and elevator equipment set
A crane lifted new equipment into the elevator equipment room as stair demolition advanced.
- West stair: joint sealants at the brick veneer column.
- East stair: pan deck cuts, temporary fencing and storefront protection, beam install, sawcutting, first-phase sandblasting, and top-down demolition of stair pans and landings.
- Elevator: governor, pit equipment, and hoistway equipment wrapped up; hall fixture installation began.
- ADA and parking: Building 1 ramp concrete and sitework, Building 4 ramp demolition and sitework, and parking lot base and paving.
Week of July 12, 2026 Complete
West stair finished as elevator machine is set
Stair and elevator replacement work spread across campus, with crews mobilizing from the west staircase to the east.
- West stair: treads and risers installed, brick cleaned and repaired, and crews mobilized to the east staircase.
- East stair: work plan laid out with temporary fencing, protection, and interior walls so occupants would not exit through the work zone.
- Elevator: new machine and rope mounted, new controller mounted and wired, governor set, and pit and hoistway equipment installed.
- ADA: continuing concrete at Buildings 2 and 4 and The Dalles parking area, plus underground utility work by Building 3.
Early summer 2026 Complete
Signage awarded and ADA work moves to the field
The program shifted from design into procurement and field work across several projects.
- Wayfinding signage advanced to fabrication, with a notice to award issued and an additional-services amendment approved to extend interior signage programming.
- The campus ADA accessibility improvements reached a pre-construction milestone with the civil and survey teams.
- Monthly billing and schedule-of-values reviews established for consistent, transparent reporting.
Spring 2026 Complete
Roofing package advances to bid
End-of-month updates were presented to the Board through the spring as key packages advanced.
- The Dalles Campus roof project reached 100% construction documents and went out to bid, with addenda issued to bidders.
- Wayfinding design and additional-services approvals moved forward.
- Civil design services engaged to support site and accessibility work.
Winter 2025-26 Complete
Design underway across priority projects
With contracts in place, design teams began developing the first bond-funded improvements
and the program settled into a steady monthly reporting rhythm.
- Design meetings launched for early priority projects.
- A year-end program update was issued summarizing progress to date.
- Alternative contracting method findings completed to enable efficient project delivery.
Fall 2025 Complete
Program launch and contracts
HMK Company was engaged to manage the capital bond program. Initial professional-services
contracts were approved and issued, and the college's bond communications plan — including
newsletters and this landing page — was established.
Nov. 5, 2024 Milestone
Voters approve Measure 33-111
Gorge voters passed the capital bond, launching the improvement program and unlocking
Oregon state matching funds. Proceeds also retired the district's existing debt,
lowering long-term interest costs.